The RM2.4 million, 550-metre link between Sections 4 and 5 started in May 2026 and is due by mid-2027.
- 01The problem
Traffic between Sections 4 and 5 bottlenecks on narrow roads also used by Smart Selangor and Rapid KL buses.
- 02The fix
A four-lane link with walkways, a raised speed table, LED lights and traffic lights at the TK5/1 junction; bus stops move about 50 m and TK5/32a becomes one-way.
- 03The proof
About 15% complete in July 2026.
- 04What's next
Progress photos every quarter until completion in mid-2027.